Town of Clayton Sanitary Sewer Construction
Project # M0015-9-20-00374
Week 14 Update 01-22-21
Week 13 Update 01-15-21
Week 12 Update 01-08-21
Week 11 Update 12-24-20
Week 10 Update 12-18-20
Week 09 Update 12-11-20
Week 06 Update 11-20-20
Week 05 Update 11-13-20
Week 04 Update 11-06-20
Week 03 Update 10-30-20
Week 02 Update 10-23-20
Week 01 Update 10-16-20
Preliminary Schedule:
Phase 1: October 12-November 13
Phase 2: October 26-December 7
Phase 3: November 16-December 28
Town of ClaytonTori Straw, Administrator Project EngineerMcMahon Associates, Inc. Ken Dreyer / Onsite Rep |
General ContractorPTS Construction Subcontractors
|